The Board approved thirteen investment projects on a total sum of $ 101,5 million, on following territories of priority development:
Donetsk:
- Limited Liability Company "Ukrtransmash”, project "Organization of bulk petrol waggons production" to the amount of $ 14 million;
- Closed Joint-Stock Company "Donetsk bread-baking plant", "Organization of modern and highly technological production", $ 4,5 million;
- Closed Joint-Stock Company "Doti", project " Organization of refrigerating machinery manufacturing for trading enterprises and public catering", $ 2,9 million;
- Closed Joint-Stock Company "Donetsk macaroni factory", "Reconstruction and mod-ernization of pasta production", $ 1,4 million;
- Limited Liability Company "Technoprofile Rubber Technological Products", "Or-ganization of non-moulded rubber products manufacturing", $1 million.
Slavyansk:
- Closed Joint-Stock Company "Zeus Ceramics", "Organization of ceramic tile produc-tion", $ 51,9 million;
- Closed Joint-Stock Company "Slavolia", "Reconstruction and modernization of the sunflower seeds processing technology", $ 10 million;
- Closed Joint-Stock Company "Garment factory" Ukrainka", " Organization of manu-facturing of jeans items and new kinds of knitted cloths", $ 1,8 million.
Gorlovka:
- Open Joint-Stock Company "Concern "Stirol", "Creation and exploitation of the nano-filtering water-purifying installation", $ 1,4 million.
Makeevka:
- "Makeevka foodstuffs plant", "Organization of both tea packing and spiceries process-ing", $ 1,3 million;
Enakievo:
- Limited Liability Company "Karina", "Modernization of sewing production", $ 1 mil-lion.
Torez:
- Limited Liability Company "The Donbass Enriching Facility", "Organization coal concentrate production", $ 4 million.
Maryinsky region:
- Limited Liability Company "Technological Center "Agrotechnologies","Creation of a hothouse complex for Dutch roses cultivation", $ 6,25 million.
The total number of newly created workplaces will make 2240, and also 1758 work-places will be saved.
On nine to the earlier approved projects the increase of the sum of the investments at $ 84,7 million was approved, under three projects – reduction for the sum of $ 2,5 mil-lion.
Besides, because of the applicants non-fulfillment of the investment obligations, the Board cancelled the effectiveness of certificates under 2 investment projects on a total sum of $ 3,76 million.
|